In brief
In the Finnish Transport Infrastructure Agency's (Väylävirasto) planning projects, self-delivery practices varied widely from one service provider to another. In 2024–2026, a common minimum requirement and templates were developed for general, road and rail planning. Nexpert was the lead service provider for the work, together with the agency's working group: it mapped the process, wrote the quality assurance texts for the management system, designed and led the expert workshops, coordinated the comment rounds, built the Excel templates and supported the rollout.
Where we started
Self-delivery (itselleluovutus) is a quality assurance method familiar from construction: whoever does the work checks it before handing it over to the client. The agency wanted to bring the same logic consistently to planning and design as well.
Practices differed widely. Some service providers carried out a very detailed self-delivery; others submitted a signed confirmation that it had been done. The gap was narrowed with two principles:
- a common minimum requirement, so that self-deliveries are of consistent quality and comparable;
- providers' own, more detailed templates are allowed – good practices are not blocked.
What Nexpert did
- We mapped the quality assurance process of planning projects from the client's perspective in general, road and rail planning.
- We described the client's quality assurance checkpoints as a process diagram and in text.
- We wrote the quality assurance texts for the agency's management system together with the agency's working group.
- We designed and facilitated expert workshops with project management and design management experts from the agency and the then ELY Centres.
- We coordinated two extensive comment rounds on the template for project managers at the agency and the ELY Centres.
- We built the Excel templates and revised them based on user feedback from the pilot.
- We produced training materials and presented the templates at various events.
- We are designing a technical follow-on solution.
The work in numbers
- 6 expert workshops
- dozens of working group meetings
- 2 comment rounds with different groups
- about 10 template versions
How the rollout progressed
- 2024 – current-state mapping and expert workshops; the first Excel versions.
- 2025 – further development of the Excel templates, presentations to the industry, pilots, user feedback and fixes.
- From February 2026 – the agency introduced the common templates in new projects.
- 2026 – a feedback round and fixes to the planning templates, and workshops on the construction-phase templates (rail, road, design-build contract). The construction planning template is expected to be published in 2027.
The published templates are available on the agency's consultant extranet.
What we learned about introducing a common way of working
- First a working process, then software. The model was tested in Excel on real projects before anything was coded.
- Every term is tied to an action. When material has been checked, reviewed or approved, it must be clear who did it, which material it covers, what record it leaves, what happens to the corrections and whether the work may proceed.
- Every role sees its own part. In the template, the fields for the designer, the internal checker, the external checker and the client are kept separate.
- The model is made with its users. The template was commented on and piloted by project managers and design management experts, as well as designers, design clients and construction clients.
These principles are not specific to the agency. They apply whenever a way of working shared by several organisations has to be put into everyday use in design packages.
Project-specific exceptions and how they are documented
The model follows the agency's technical and safety guidelines and sets the baseline minimum level for self-delivery. Project-specific practices can still be agreed, with justification, within the latitude the guidelines allow. For example, in a small pedestrian and cycle path project, self-delivery can be carried out more lightly. The agreed practices and their justification are recorded in the minutes of design meetings. The guidelines and the latitude they allow are described in the planning management system under the activity concerned.
Recommendation
“A developer of continuous improvement and LEAN tools. Tanja is efficient and gets things done, has an enthusiastic attitude and is adept with digital tools. I warmly recommend Tanja.”
Development Manager, Finnish Transport Infrastructure Agency
Go deeper
- One View for the Entire Quality Assurance Process – how the template works in practice and what each role records in it.
- Data quality starts with a common terminology – why checked, reviewed and approved must be kept apart.
- Quality assurance in the infrastructure sector from the Excel phase to the era of artificial intelligence – the stages of three years of development work.
- Automated quality assurance and self-dissemination of design: Bridget App – where the work could lead next.
Finally
If you already have a clear way to put a shared way of working into everyday use in your design packages, there is no need to rebuild it. If you would like to compare experiences, get in touch: tanja@nexpert.fi.
We also offer training in using the agency's self-delivery templates for designers, internal checkers, quality assurance staff, project managers and design clients.